Current Project: 253 Portobello Road, Notting Hill, London


G3 Construction UK Ltd. are currently working on a project at 253, Portobello Road in Notting Hill, London on behalf of A&E Elkins Ltd.

The works are described as the following: 'external alterations, rear extension at first-floor level and associated internal alterations in association with upgraded class A1 and A3 use'. Ultimately, 3 retail units and a restaurant are being refurbished. It is planned that the fabric of the building will be remodelled completely.

The first phase of works began on the 14th August 2017 for a duration of 4 weeks. This phase includes: 1) Complete strip out and demolition of whole building and 2) Removal of all non-structural, internal walls to create a shell.

The second phase, basement structural works (including foundations steelwork and underpinning) began on the 28th August and will endure for 6 weeks.

Furthermore, the third phase being electrical works will begin on the 11th September and is expected to continue for 8 weeks.

The fourth stage, mechanical works, will begin on the 25th September for a duration of 8 weeks.